Oyster Creek

Basic Facts:

  • Location: Forked River, New Jersey
  • Owner: Exelon
  • Operator: Exelon
  • Construction Cost: $600M (2018$)
  • Plant Output: 620 MW
  • Property Size: 800 acres
  • Status: Decommissioning
  • Current DTF Balance: $930M (2018$)
  • DTF Balance Prior to Decommissioning: $980M (2018$)
  • Decommissioning Cost Estimate: $1.2B (2018$)
  • Spent Nuclear Fuel on Site: 707 metric tons
oyster creek

Background

The Oyster Creek Generating Station first came online in 1969, received a license renewal from the NRC in 2009 and was licensed to operate until 2029. In 2011, Exelon informed the NRC that in 2019 the plant would permanently cease power operations due to economic considerations. In September 2018, Exelon ceased operations at Oyster Creek and the plant was permanently shut down.

Decommissioning

In July of 2018, Exelon announced a decommissioning agreement with Holtec International. Under the terms of the agreement, Holtec will assume ownership of the site, real property and spent nuclear fuel. In addition, and as the site’s owner, Holtec will manage all site decommissioning and restoration activities. The agreement is subject to regulatory approvals.

Socioeconomics

The Oyster Creek nuclear power plant is located within Ocean County, New Jersey.  As of 2016:

  • Population: 600,000
  • Per Capita Annual Income: $32,000
  • Unemployment rate (not seasonally adjusted): 4.3%

During operations, the Oyster Creek Generating Station employed 450 people with an annual payroll of approximately $70M. In 2017, the plant contributed $2.5M in property tax payments.

Contact Information

Economic Development Administration Representative:

  • Edward Hummel, Philadelphia Regional Office, t: (215) 316-2124, e: ehummel@eda.gov

Nuclear Regulatory Commission Contact

Unless specific costing information has been provided, decommissioning costs were derived from 2017 Decommissioning Funding Status Report.
Information herein obtained from public sources. Corrections are welcome and may be directed to info@decommissioningcollaborative.org.

Additional Information

Nuclear Regulatory Commission Hears Citizens Request for Advisory Board

October 7, 2019

Andy Kim holds town hall on decommissioning of Oyster Creek plant

September 1, 2019

Andy Kim To Hold Lacey Town Hall On Oyster Creek Plant

August 4, 2019

SNC-Lavalin’s CDI joint venture company closes deal to decommission US Oyster Creek nuclear power plant

August 4, 2019

New Nuclear Plant Owners Plan to Begin Immediate Decommissioning

July 14, 2019

New Nuclear Plant Owners Plan to Begin Immediate Decommissioning

July 10, 2019

Holtec Seals Deal for Oyster Creek Plant

July 9, 2019

Oyster Creek: Stay on top of nuclear plant decommissioning to protect wallets, safety

June 29, 2019

Oyster Creek License Transfer Approved Amid Questions Of Process

June 27, 2019

Oyster Creek licence transfer approved

June 24, 2019

(802) 345-7044

info@decommissioningcollaborative.org

Connect

Blog

Contact

Download our

free report

Discover tools and information for improving project outcomes and
catalyzing economic recovery

Scroll to Top