Basic Facts:
- Location: Delta, Pennsylvania
- Owner: Exelon (50%) PSEG (50%)
- Operator: Exelon
- Plant Output: 40 MW
- Property Size: 620 acres
- Status: SAFSTOR
- Current DTF Balance: $110M (2018$)
- Decommissioning Cost Estimate: $260M (2018$)
- Spent Nuclear Fuel on Site: None
Background
Peach Bottom 1 was an experimental helium-cooled, graphite-moderated reactor. Construction of Peach Bottom 1 started in 1962 and the plant began licensed operations in 1966. In 1974, 1974 Peach Bottom 1 was shut down.
Socioeconomics
The Peach Bottom nuclear power plant is located within York County, Pennsylvania. As of 2016, socioeconomic information is as follows:
- Population: 446,000
- Per Capita Annual Income: $46,000
- Unemployment rate (not seasonally adjusted): 4.0%
Contact Information
Economic Development Administration Representative:
- Christopher Casper, Philadelphia Regional Office, t: (215) 597-1074, e: [email protected]
Nuclear Regulatory Commission
- Zahira Cruz, Project Manager, t: (301) 415-3808, e: [email protected]
- Peach Bottom 1
Unless specific costing information has been provided, decommissioning costs were derived from 2017 Decommissioning Funding Status Report.
Information herein obtained from public sources. Corrections are welcome and may be directed to [email protected].
Additional Information
Process to decommission Peach Bottom reactor to begin in fall, active work planned in 2028